A year ago, Energy Secretary Chris Wright directed federal regulators to speed up how data centers and other large power users get connected to the grid. Then in June, the Federal Energy Regulatory Commission’s initial view was that the existing rules fell short; it ordered the six grid operators it oversees to show how they would fix them.
By Nov. 16, five had answered. The sixth, the Southwest Power Pool, is due to file by Nov. 20.
The operators’ plans are, unsurprisingly, mostly about speed. The plans focus on shorter timelines and earlier connections for data centers. PJM would study new load and new generation together in a single 12-month process, for example. New York and California took similar approaches, both proposing to let data centers connect faster to the grid if they agree to curtail during periods of congestion.
But the operators weren’t the only ones to file on Nov 16. The utilities that own the transmission lines also sent in their own proposals, grouped by region. Their responses tackle a different question: not how to get loads connected faster, but rather who pays for the associated grid upgrades and for how long?
And while each takes a different approach to answering that question, together they are asking FERC to endorse an approach where data centers sign a long-term contract with the utility that owns the relevant lines before the upgrades it needs can get built.
For the utilities in PJM’s region, a data center would commit to paying for at least 80% of the transmission service it requests for a minimum of 10 years, backed by collateral. In California and New York, the term would be 15 years. The Midwest is proposing a more unusual set-up, as its main grid operator, MISO, pitched the contract itself: a three-way agreement with the utility and the data center that would run up to 20 years.
If those commitments look familiar, it’s because they are. Many of the same utilities already require similar terms for data center customers under tariffs their state regulators approved. Now, though, they’re using the show-cause order as an opportunity to ask FERC to approve something similar — though crucially, not exactly the same. The federal proposals ask data centers for longer commitments in some places, and shorter ones in others.
What a data center would sign
A data center’s power bill is regulated in two places. The state utility commission approves the utility’s tariff, which sets what the customer pays for local lines, power plants, and, in some states, transmission. Then FERC regulates the high-voltage grid, which is where the new contracts would sit.
These new contracts cover only transmission and don’t replace the state tariff, so a data center could end up signing two parallel, but not identical, sets of terms.
For utilities in PJM, the federal half would be a cost recovery agreement that the data center signs directly with the transmission owner, requiring the data center to pay at least 80% of its expected transmission charges. The data center would also have to put up a financial guarantee starting at 25% of what it would owe, and increasing to the full amount by the time service begins. A data center that leaves early would owe the transmission owner the rest.
State-approved utility tariffs work the same way, setting both a minimum bill and an exit fee, meaning that there’s a floor that the customer pays whether or not it uses the power, and a charge for walking away. Dominion Energy’s large load tariff in Virginia, approved last year and taking effect in January, sets that floor at 85% of contracted transmission demand over 14 years; AEP Ohio, meanwhile, requires 85% over 12 years.
Longer terms in some regions, shorter in others
Compared with what utilities already require under their state tariffs, the federal proposals would lengthen a data center’s commitment to pay in some regions and shorten it in others.
According to a Latitude Intelligence analysis, utilities in PJM whose state tariffs require a transmission commitment hold data centers to an average minimum of 12 years. Their joint filing at FERC, though, proposes a floor of 10 years. In MISO, utility terms average 15 years; the grid operator’s proposed contract would run up to 20 years. In California and New York, where the state-approved tariffs set no minimum term at all, a 15-year contract would be the first long-term commitment of any kind.

The biggest change would be inside PJM, in states with retail choice such as New Jersey and Pennsylvania. There the customer pays for transmission through a power supplier, so a utility’s minimum bill generally doesn’t apply, even under the data center tariffs now pending at utilities such as PECO and PSE&G. The federal agreement, therefore, would become a data center’s only long-term commitment to pay for transmission upgrades.
Utilities were also careful to make clear what their filings don’t cover. The PJM group wrote that their proposal does not “establish or govern any terms and conditions of retail service.” The New York contract and Southern California Edison’s filing draw the same line, leaving retail rates to state regulators.
That leaves most of a data center’s cost to each utility’s own tariff. Local wires and power plants are paid for under retail rules, and in several of the largest markets utilities still have no data center terms in force, even after the show-cause proposals.
One of those utilities is Northern California’s PG&E. At PG&E, the federal contract would be the only long-term commitment a data center would sign, at least for now. The utility reports a data center pipeline of 12.9 gigawatts, and its retail schedule sets no minimum term and no minimum bill.
California passed a law in September ordering utilities to implement large load tariffs by 2028. Until then, though, a data center in the state would be bound for 15 years on the federal contract, but have no long-term commitment to cover local wires or power plants.
Niagara Mohawk, National Grid’s upstate New York utility, is in the same position, with an even longer wait. It sets no minimum term for data centers today, and the 15-year contract that New York’s utilities jointly proposed wouldn’t take effect until May 2028. Until then, a data center there would have no long-term commitment at all.
None of these federal contracts are final, however. The show-cause order was just a first step. FERC has to accept the proposals; comments on several are due Dec. 7. The commission rejected most of PJM’s last large load plan in October, in part for overreaching into retail territory. It’s possible it will come to the same conclusion about some of these proposals for contracts signed directly with data centers.
There’s a good chance that this process leaves the country with a state versus federal patchwork of rules for data centers to navigate. The PJM utilities asked that existing contracts between a utility and a data center be allowed to stand in for the new one where they offer comparable protection. If FERC agrees, a data center in Virginia would keep the contract it has, and one in Pennsylvania would get the federal one.
Pending filings, signed load, and tariff terms for the utilities in this piece are tracked on the Latitude Intelligence platform