At long last: a publicly traded artificial intelligence lab. Anthropic is expected to price its initial public offering later today, ahead of tomorrow’s first trading on the Nasdaq, ticker symbol ANT. The potentially historic IPO — the company plans to sell 825 million shares at between $70 and $78 — lands at a time when market confidence in the AI boom is at an inflection point.
Nvidia ousted CEO Jensen Huang over his multiple affairs, including one with a Chinese spy; the blue wave midterm election involved a significant data center backlash; there are signs of a slowdown in data center construction. And all come just as investors have grown concerned about AI’s promise and enormous expenditures.
But if the AI bubble appeared to be losing some air, Anthropic’s market debut and a strong showing in Nvidia’s earnings yesterday might pump things up again, according to Morningstar senior equity analyst Travis Miller. And that’s good news for the many energy companies that have served the boom; Miller monitors electric utilities, which he said have had a “rough” couple of weeks.
“Utilities and investors are watching the landscape very closely because data center growth is a key part of the investment story for utilities in the coming years,” Miller said. “Can utilities continue to live up to investor expectations of growth if the bubble is deflating?”
Anthropic’s updated financial report to the Securities and Exchange Commission walks through the infrastructure buildout that the company sees ahead (a lot) and how the company is thinking about energy (also a lot).
As an AI lab, of course, Anthropic doesn’t develop data centers itself. But it contracts a huge, and swiftly growing, number of them. They rely heavily on fossil fuels, according to a recent analysis, and Anthropic’s prospectus includes little encouragement for clean energy suppliers. The company makes just one brief mention of clean energy sources such as solar, wind, battery storage, nuclear, and geothermal power, warning that those “may not be available in the quantities or on the timelines we require, or may be available only at higher cost.”
Anthropic said that construction in progress on the company’s behalf as of the end of September 2026 totaled $877 million. That pales in comparison to the purchase commitments and lease agreements the company has in place, with an aggregate committed spend of approximately $895.4 billion, “substantially all of which is related to compute and infrastructure.”
The document also established a rough timeline for that infrastructure spending. About $69.8 billion is slated for the coming year. Approximately $447.5 billion is expected by 2030, and most of the remainder is expected between 2031 and 2045. “As our compute and infrastructure capacity grows, the associated compute and infrastructure expenses have increased,” Anthropic said in the filing.
Energy concerns are clearly front of mind. The company dedicated much of its assessment of risks to a discussion of the variability and uncertainties of power supplies and regulations.
“Electric grid infrastructure in the United States and other countries was not designed to accommodate the rapid increase in demand associated with AI development,” the AI lab wrote.
Anthropic is primarily turning to natural gas to power its tremendous need for new compute. Last week the Financial Times reported that Anthropic struck a $3.4 billion deal for more gas-fired generators, getting commitments from Texas-based OnePWR Solutions for 1.7 GW of generator power.
An analysis of Anthropic’s energy use by the nonprofit Better Data Center Project reveals just how fossil-bound the company is. The researcher’s case study found that Anthropic has made no direct commitments to renewable energy in the U.S.
The company’s data centers are mostly sited in areas where the grid relies heavily on coal and gas, and “currently contracted data centers in the U.S. will be overwhelmingly powered by fossil fuels in the near term.” Lacking commitments to clean energy, the additional demand on the grid post-IPO will likely mean more fossil infrastructure. When the company uses behind-the-meter sources, the researchers said, the gas-burning turbines are often less efficient and more polluting.
“By considering on-site gas and the grid power plants which are likely to meet Anthropic’s added load, we estimate about 87% of the company’s power will come from gas and 11% from coal in 2028,” the researchers concluded.
The energy impacts of a weird AI week
Anthropic’s debut comes just a little more than 24 hours after a much-watched Nvidia earnings call Tuesday evening, where the chip giant shared stronger-than-expected third-quarter earnings following a tumultuous two weeks that saw the ouster of charismatic CEO Jensen Huang, a spy scandal, and a swoon in share prices.
The call’s tone was calm and confident as interim CEO Colette Kress and board director Harvey Jones sought to reassure jittery investors that Nvidia was shaking off its Huang-over. Jones put to rest rumors of Huang’s possible return; Kress opened her remarks with “our momentum is real” and closed with “we’ve got this.” In between, she raised sales guidance for the coming year from 70% to 75% expected growth and said that commitments to partners will not change.
Kress also addressed the status of the PORTS-Pike Technology Campus, a massive facility that SB Energy, a SoftBank subsidiary, is developing in southern Ohio with Anthropic’s chief competitor OpenAI as the tenant. The project relies on an unusually tangled financing arrangement, and SoftBank recently canceled some advance payments for power equipment for its U.S. data center projects, raising some doubts. Kress said Nvidia has $105 billion in credit support for land, power, and shell capacity for the PORTS Pike campus and that “plans are on track, with capacity expected to come online in phases beginning in calendar [year] 2028.”
Investor confidence in the pace of the AI buildout was waning in the weeks leading up to Anthropic’s launch, and two recent analyses point to a recent downturn in the pace of data center development.
Market intelligence company Cleanview found that new data center construction in the last quarter fell 28% compared to the previous quarter, the first such drop since early last year. However, construction is still twice last year’s pace, so it is unclear if the slowdown is a blip or a longer trend.
Meanwhile, the Financial Times analyzed the change in total market capitalization over the year for the energy, manufacturing, and mining companies closely associated with the AI infrastructure buildout — and found a sharp drop in the later months of 2026.
Caterpillar, which supplies gas generators to data centers, saw market cap fall 44% per cent, since June 30. Fuel cell company Bloom Energy enjoyed a 300% increase in market cap in the first 6 months of 2026, but that measure dropped more than 30% between June and November. And advanced nuclear company Oklo dropped nearly 50% despite the company’s agreement with Meta.
“Any pullback in demand could cause a hit,” Miller said.