About 20 miles southeast of Bend, Ore., hot rocks lurk below the surface of cauldron-like hills and an expansive obsidian formation. The area, known as the Newberry Volcano, is a major testing ground for enhanced geothermal systems due to its extreme underground heat.
The startup Quaise Energy is among the new entrants to the region, but it’s moving fast. It made headlines this fall for receiving a $25 million grant from the Department of Energy and striking a 50-megawatt power purchase agreement with Google just last week. Last year, the company secured approval for exploration and drilling on federally managed land, after the Trump administration accelerated geothermal permits across Western states. It aims to deliver its first 50 MW of electricity to the Pacific Northwest grid in 2030, according to a company spokesperson.
Quaise’s momentum comes on the heels of its larger and better-capitalized peer Fervo’s nearly $2 billion IPO in the spring. Fervo is ahead in terms of tech maturity, offtake agreements, and financing, with many other players still in the wildcatting phase: scouring the U.S. for the best resources, drilling wells, and trying to validate their approach. Post-IPO, market and financial analysts are still questioning whether the more than a dozen other startups in the space will be able to replicate Fervo’s success.
They told Latitude Media that whether the industry can unlock power at gigawatt scale in the coming years likely relies on several major breakthroughs: how Fervo’s Cape Station performs; whether Congress’ can pass permitting reform that yields much faster timelines for building big energy projects like transmissions lines — critical infrastructure to the geothermal industry — and whether the oil and gas industry brings in massive balance sheets.
“If you need to spend $10 [million] to $30 million to prove out the resource in the exploration phase, that’s not an issue for Chevron,” Guy Cohen, senior research associate at Currence, told Latitude Media. Startups typically build 20- to 100-megawatt projects, he added, but oil majors could fund gigawatt-scale ones.
Research analysts at Bank of America made a similar observation in a Nov. 20 note to investors. While startups have accelerated innovation, they said, delivering multiple gigawatts on shorter timelines will likely require greater investment from oil and gas majors.
If one or more major fossil fuel company commits to a multi-GW project for a large power buyer, that could validate the market and accelerate investment across the supply chain, the note said, which summarized a call with Jamie Beard, founder and executive director of Project InnerSpace, a geothermal research nonprofit.
Chevron, Devon Energy, and Occidental Petroleum are all dabbling in EGS. Chevron’s low-carbon business has spent venture capital on firms like Eavor, and has quietly been buying up geothermal acreage in the West, Cohen said. Meanwhile, Devon has invested nearly $200 million into Fervo and lent its shale drilling expertise to help cut the company’s drilling times by 70%, according to a review of its financial disclosures.
Scaling up
But investors are still wary. Fervo’s stock dropped about 70% since its debut in May amid concerns about the massive capital needed to expand its first commercial plant in Utah, called Cape Station, which delivered its first 33 megawatts of power in September.
Transmission bottlenecks are also undercutting confidence in the market. And companies are still testing a wide range of different ESG technologies to unlock geothermal power in more geological formations than past approaches that were limited to naturally occurring hotspots.
As a result, the sector remains a risky bet for traditional infrastructure investors. It instead relies on a mix of venture capital, strategic power purchase agreements with hyperscalers and utilities, and DOE grants, according to Rebecca Rogers, a partner at law firm Foley Hoag who advises on renewable and geothermal project finance.
“Project finance hates uncertainty, and they hate variation because it leads to uncertainty,” Rogers told Latitude Media. “This is still largely wildcatting. You have to pick a 30-square-foot location and punch a hole in the ground. That’s a really costly decision.”
Quaise, for its part, said it’s using “conventional” oilfield drilling technology for its initial phase of development in Oregon. The startup had raised $280 million as of August. Quaise is also developing millimeter wave technology that beams through some of the hottest rocks on Earth, known as “superhot” geothermal, spokesperson Diane Hughes said in an email.
Fervo followed a similar financing pathway up until its IPO in May. Cohen of Currence said the nearest term bellwether for the industry is what happens at Fervo’s Cape Station as it expands over the next couple years. Data on drilling costs, repeatability, and sustained thermal output will be closely watched — and ultimately will likely determine whether EGS can attract bigger pools of capital, especially from oil and gas majors.
“How it performs in the first year or two will really indicate how many people are going to rush in with how much capital, how fast,” Cohen said. “Anything before those data points, you’re kind of like, is EGS something that’s kind of cool and will improve over a long time, or will there be a flip much sooner, where those oil majors come in each doing gigawatt-sized [projects]? Those things are up in the air.”
Is geothermal getting what it wants from Trump?
On the policy front, the industry already has allies in the Trump administration. Energy Secretary Chris Wright — former founder and CEO of the fracking company Liberty Energy — is a longtime supporter of geothermal. Liberty was an early investor in Fervo’s EGS technology with a $10 million in 2022, and Wright has been vocal about the industry’s potential.
Shortly after Trump launched his energy dominance agenda in early 2025, DOE folded its geothermal work into a hydrocarbons office, a logical play for Wright that signaled the push to transfer oil-and-gas drilling expertise into the industry.
The Biden administration had already laid a lot of the groundwork for advancing EGS, especially once the bipartisan infrastructure law funneled hundreds of millions of dollars into research and demonstration projects, including a partnership with the oil and gas industry. The 2022 Inflation Reduction Act also included investment and production tax credits for the industry, which Wright personally fought to preserve in the GOP’s One Big Beautiful Bill that phased out subsidies for solar and wind power last year.
The Biden administration also took steps to speed up geothermal projects on federal lands, finalizing “categorical exclusions” for activities like small, early-stage exploration and well testing that exempts them from multi-year environmental reviews under the National Environmental Policy Act. Trump’s Department of Interior has since accelerated federal lease auctions and approvals of such projects, including for enhanced geothermal like Quaise Energy’s work in Oregon.
The Bureau of Land Management, which operates from within Interior, approved the company’s categorical exclusion in September 2025, and by July of this year Quaise announced it began drilling its first well. Just two months later, the startup was among 14 other companies and research groups that received a combined $99 million in DOE grants. The list included those already doing field-scale tests — like Quaise, Fervo, and Zanskar — as well as those in the earlier stages of gathering data that determines whether a site has promising enough geothermal resources to start drilling.
But a federal watchdog in October identified some problems in BLM’s geothermal permitting process, such as a knowledge gap between BLM staff and geothermal developers and no way to track the status of permits across its field offices. Meanwhile, the Senate’s permitting reform bill also would require BLM to hold annual geothermal lease sales and allow industry fees to fund more permitting staff at the department.