It’s going to be a strange winter for Texas data center developers, and for the companies betting on providing them with power. They were already waiting to hear the results of Gov. Greg Abbott’s data center audit, which stopped approving grid connections for new data centers and crypto mines of 75 megawatts or more until regulators have the chance to review them.
So far, ERCOT has provisionally let some 200 projects totaling 66.4 gigawatts keep their place in line, and has already shut out over 350 projects totaling more than 300 GW. That leaves nearly 170 GW worth of projects still waiting for the Texas green light, according to a Latitude Intelligence analysis of the queue.
Clarity on the review process, known as “Batch Zero,” has long been expected in December. But then Democrat Gina Hinojosa won the election for governor, ending the GOP’s 30-year run in the governor’s mansion, and raising questions about how and if she’ll maintain Gov. Abbott’s plans.

The state is the second-largest data center market in the U.S., and in her campaign, Hinojosa blamed Abbott for that explosive growth; Abbott just a year ago declared Texas the “epicenter of AI development,” and offered incentives for qualifying data centers looking to build in the state. Hinojosa said she would block new construction until state lawmakers can pass stronger restrictions, including on water and energy use. She takes office on January 19, 2027.
Of course, Hinojosa can’t do everything on her own. Passing laws like Senate Bill 6, which rewrote the rules for how large loads connect to and operate on the grid, requires lawmaker cooperation — and after Democrats also took the statehouse this month, 2027 will be the first time in 25 years that there will be a partisan split in the legislature. But her predecessor froze the load queue via letters to the Public Utilities Commission, ERCOT, and the Texas Commission on Environmental Quality, which means that Hinojosa can do the same.
Analysts for the investment bank Jefferies said in a post-election note that they’re skeptical that the new governor will reverse changes already implemented by Abbott. Instead, they anticipate that “the most plausible policy outcome is a legislative compromise that codifies consumer protections and sets guardrails on large-scale development.”
“The pause could be long,” they added, though they “expect Texas to build significant data centers in 2028 [and beyond]. Those already underway appear to be accelerating.”
The reasoning behind the Abbott pause, as well as Hinojosa’s stated plans, includes concerns about whether data centers are driving up costs for ratepayers. But because of the peculiarities of the Texas market, the absence of new data centers could also have a direct impact on prices, both for consumers and for power producers. Wholesale power for future years already trades at prices that assume, according to Jefferies, about six GW of grid-connected data centers each year. If those facilities don’t arrive, those prices fall. That is good for bills, and bad for the companies that own power plants.
The market is already responding to the potential that data center development will slow; both NRG and Vistra stock prices fell 14% post-election.
The decisions to come
Elizabeth K. Whitney, managing principal at the government relations firm Meguire Whitney, said data centers are certainly concerned about what a blue Texas could mean for their work. But there’s a potential bright side, she added: Once the state has regulation finalized, especially rules that have been touched by leaders in both parties, that will give future facilities more certainty about the policy regime they’re building under. That’s more than they have in much of the country.
And times had been changing in Texas since long before the election, she pointed out. “If you were thinking that it would be the laissez-faire Wild West forever, your first indication probably should have been Gov. Abbott instituting his pause on new interconnections,” Whitney said.
In Abbott’s last months in office, there are a few key dates for data centers and the energy companies that power them: On Dec. 10, ERCOT will file its verification and community impact reports for the data centers in the queue, which will determine which facilities “passed” the audit. Then on Dec. 17, the state’s current PUC will meet for what may be its last time. (Public utility commissioners have staggered appointments by the governor in Texas, so it’s likely that Gov.-elect Hinojosa will reconfigure some of the group’s make-up.) Their meeting will be the first action on which facilities keep a place in the Batch Zero line. Final Batch Zero classifications are due sometime in December.
But no matter what happens, there are no guarantees even for the data centers who get rubber-stamped next month. In between mid-December and mid-January, those that make it through the Batch Zero process will be in limbo. A project that clears the audit in December will still need for ERCOT to restart approvals and for the state to lift the permit freeze — and both of those decisions will fall on Hinojosa.
Joshua Rhodes, a research scientist with the Webber Energy Group at the University of Texas at Austin, pointed out that this process was always first-of-a-kind and therefore uncertain; the partisan flip is just an added layer of confusion. “It was always a bit unclear how [the information in the audit] was going to be used,” Rhodes said. “And I think it’s probably going to be a lot more scrutinized now.”
An opportunity for influence?
Of course, there are large loads that need power other than data centers; Texas’ manufacturing output is accelerating “sharply” this year according to the Federal Reserve Bank of Dallas. But data centers are by far the biggest opportunity. In June, ERCOT reported that of its 474-GW pipeline of large loads that it is tracking, roughly 90% are data centers.
As a result Rhodes and Whitney emphasized that this window of data center limbo, and especially the months after Gov.-elect Hinojosa takes office, offers a key opportunity for energy companies looking to influence the new policy regime for what has become a major market for emerging energy technologies.
“This will be a negotiation, and that people shouldn’t assume that because a certain party or certain individuals are in power that the policy outcomes are a foregone conclusion,” Whitney said. “It’s really important to be in those rooms and be part of those discussions.”
She distinguished between a process that is focused entirely on restricting data centers, versus one focused on bolstering the grid to ready it for the influx of large loads. “Will policymakers treat the grid as something that’s relatively static, and continue to delegate operational authority to ERCOT and Texas PUC? Or will they pick up the pen and start thinking about how the grid needs to be reimagined in order to accommodate data centers?” she asked rhetorically.
Choosing the latter path, she said, could include embracing grid flexibility or grid utilization or more clean energy on the grid — and it’s on energy solutions providers to pitch those options for “the dual benefit of reducing system costs and providing flexibility, while [bringing] more affordability benefits to consumers.’”
Rhodes agreed, and emphasized that a blue Texas may require energy companies to change how they talk about their work. “In terms of influencing policy in Texas, you’ve only really had to speak Republican for the past 30 years,” he said. “But for the next little while, you’re going to have to learn how to speak Democrat too.”