In the last two years, expectations that any meaningful portion of new data centers will operate entirely islanded from the grid have been significantly tempered. But data center developers are still embracing off-grid power solutions to help get online more quickly.
While gas will be the dominant source of power, according to analysis from Latitude Intelligence, clean energy developers see an opportunity, too.
Building islanded power projects introduces new risks. But Kevin Smith, CEO of Cypress Creek Energy, a developer that builds solar and storage, said that company would be willing to do off-grid deals, providing certain commercial terms are met.
The company’s strong preference is to build projects that then sell power directly to the grid, Smith explained. That’s because doing an off-grid project “is like 3X the complexity of doing a grid-connected project, especially when you look at the reliability requirements that the hyperscalers are looking for in their data center.”
But there are a few contract terms that could shift the risks enough to make an off-grid project amenable to the company, Smith added. They include a guarantee that protects Cypress Creek’s investment if the data center doesn’t end up needing the power or pulls back early, and limits on the penalties Cypress Creek would face for failing to deliver the promised reliability. Such protections ensure the company isn’t on the hook for costs if a hyperscaler leaves.
Hyperscalers generally require “five nines” of reliability — nearly 100% uptime — and substantial pre-determined damages if the supplier falls short, Smith explained. “That’s technically very difficult to do.”
He added that power facilities have a 30- to 40-year useful life. But it’s less clear how quickly data centers become outdated, which is an added risk for off-grid power projects.
“Does that data center become outdated in five years? And now you’ve got a 40-year power plant attached to a five- to seven-year data center,” he said. “If you’re grid connected and you have a problem with your power contract, you can always find another buyer for that power.”
For now, Cypress Creek’s largest data center-connected project follows Smith’s preferred grid-tied model. The Steel River Energy Center in Mississippi County, Arkansas will send its power to the grid via Entergy Arkansas, rather than directly to Google’s data centers in the region. Google is an anchor investor and offtaker for its first two phases, which are expected to add 1.6 GWdc of solar generation and 1.9 GWh of battery storage to the regional grid. The full three-phase project is expected to reach 2.5 GW of solar and 2.9 GWh of storage when fully operational in 2029.
Different contracts, similar risks
It’s not only off-grid solutions spurring concerns about stranded infrastructure. Front-of-meter projects are, too, which is already reshaping utility service agreements. A Latitude Intelligence analysis earlier this year found that tariffs increasingly include minimum bills, long-term commitments, and collateral requirements. Fifteen of 25 tariffs examined in the analysis included numerical billing floors, averaging around 80% of contracted demand.
Those terms can be steep. AEP Ohio, for example, requires an 85% billing floor over an eight-year minimum term after a ramp-up period. FPL locks customers in for 20 years, and Dominion Energy Virginia requires collateral of $1.5 million per megawatt, or $150 million posted upfront for a 100 MW facility.
Utilities are now seeking additional protection on the transmission side as well. In filings responding to the Federal Energy Regulatory Commission’s show-cause orders, PJM transmission owners proposed requiring data centers to pay for at least 80% of expected transmission charges for a minimum of 10 years, backed by collateral. Those proposed obligations, which have not been approved by FERC, would cover transmission only, not replace state-approved retail tariffs.
Those provisions reflect the same concern Smith raises: ensuring a customer’s commitment is long enough and financially secure enough to support the infrastructure built to serve it. Utilities are seeking that protection through service agreements and tariffs, but for developers supplying dedicated power, it remains a matter of negotiation. As Smith put it: “If the plant is paid back within five to seven years, then we’re all aligned.”